The calculation of the time limit for the overall permit-granting process starts when the authority processing the matter concludes that the first application contains the required information or when the environmental impact assessment report has been submitted to the authority. The calculation of the time limit ends when the authority issues its decision on the last application.
We will notify the party responsible for the project of the start and end of the time limit calculation and of any changes.
The time limits for the overall permit procedure for the strategic project are as follows:
- 27 months when the project involves extraction
- 15 months when the project only involves processing or recycling
If a project has already been subject to the permit-granting process before being recognised as a Strategic Project, the total permit-granting process may not exceed:
- 24 months for projects involving extraction
- 12 months for projects only involving processing or recycling.
If a project requires an environmental impact assessment, the calculation of the time limit for the overall permit-granting process starts once the assessment report has been submitted. If the assessment needs to be supplemented after a consultation, the period between the time limit for delivering the supplement and the delivery of the submission is not included in the duration of the overall permit-granting process.
No sanctions are imposed on the authorities if the time limits for the overall permit-granting process are exceeded. However, the Finnish State must ensure that the authorities processing the matter have sufficient resources and personnel to process matters within the time limits laid down in the EU regulation. In addition, the authorities responsible for the project and participating in the overall permit-granting process must ensure that the overall permit-granting process is feasible within the determined time limits.